Opening Meeting to verify the scope of the assessment and explain the method of
reporting. Top management should attend this session but the Team Leader will
take the chair.
15
9:15 - 9:30 E
External complaint/Change in the system and the documentation/Verify the
effectiveness of the corrective action since previous audit (if any)
15
9:30 - 10:30 E Site Tour 60
10:30 - 12:00 E Management Process / Management Review 90
Objectives, Planning, and Change control (Document & System)
Manual / Use of logo
E Internal Audit
12:00 - 12:45 E Office(s) , Administration activities (s) *Envi -aspects approach 45
12:00 - 13:00 Lunch 75
13:00 - 15:00 E Legal & other requirement / Evaluation of compliance 120
15:00 - 15:15 Preparation for Feedback / Closing Meeting 15
15:15 - 15:30 Feedback / Closing Meeting