If the Contractor shall fail to achieve completion the Contract Works within the time
prescribed in the Contract or such extended time allowed under Clause 12 then the Contractor
shall pay to the Employer the sum stated in Appendix A (Amount of Liquidated Damages) as
liquidated damages for such default for every day which shall elapse between the time
prescribed or extended and the Date of Practical Completion of the Contract Works.The Employer shall be entitled to deduct the liquidated damages from any monies due to the
Contractor under the Contract.