There is the specific requirments in ITB for Preparation of Punch List covering all items that are not completed/deviated from PROJECT SPECIFICATION, and categorize each item as Priority 1 (items to be remedied/completed before MC) and 2 (items are allowed to be remedied/completed after MC)