This is to report the further action plan about water leaking this month
will be for repair work which is as follows;
Date : Friday 20, from 14:00 - 18:00 the work is;
Remove entirely Vinyl Tile floor in canteen room
Remove carpet in front of canteen room
to clean and liquid chemical to protect moisture and fungicides
Date : Saturday 21, from 08:30-20:00 the work is;
Lay new entirely Vinyl Tile floor in canteen room
Re-Paving carpet in front of canteen room
Paint wall beside the Window glass entire in canteen room