There had been planning delays and the client/developer had had to really squeeze the programme. The tendering Main Contractor’s had all quoted overall programmes around 24 months and ‘on-site’ installation periods of approximately 20 months. During tender negotiations with the Developer’s agents, the successful Main Contractor, Lasrena agreed to reduce its on-site programme period to 17 months.