In this context, the jack-up vessel specific inputs [1–15] are
listed in Table 6. If the vessel is purchased, the inputs [2–6] are not
taken into account. For the fix of fail alternative, there is a
significant uncertainty on the mobilisation time due to the
insufficient number of jack-up vessels in the offshore wind market.
Therefore, the mobilisation time for the jack-up vessel operations
is defined through the selection of a random value from a
triangular distribution, for which the lower limit, mode and upper
limit are indicated by the inputs [3–5], respectively