4.2 Master schedule
This section should define the schedule for the review, proofs and
tracing activities in the phase.
Reviews of large systems should be broken down by subsystem. In
the DD phase, critical design reviews of subsystems should be held when
the subsystem is ready, not when all subsystems have been designed.
4.3 Resources summary
This section should summarise the resources needed to perform
reviews, proofs and tracing such as staff, computer facilities, and software
tools.
4.4 Responsibilities
This section should define the specific responsibilities associated
with the roles described in section 4.1.
4.5 Tools, techniques and methods
This section should identify the software tools, techniques and
methods used for reviews, proofs and tracing in the phase. Training plans
for the tools, techniques and methods may be included.