THEORETICAL CALCULATION OF NUMBER OF OPERATORS: Sum of mean time =949 seconds Takt Time = 127.5 seconds Number of operators required = (Cycle Time) / Takt Time = 949/127.5 = 7.5 Hence 8 operators are required to meet the current customer demand