Released runnung tools.
Circulation, pumping 1 m.3 brine then pumping 3 m.3 hi-vis then displace WBM by brine.
POOH to tubing liner tools.
Retrive wear bushing flush BOP then change 2 7/8" elevator for tubing hanger.
RIH 5 joint tubing hanger.
R/D bell nipple and BOP.
Install v-door and mouse hole.
Install capsil and L/D 5 stands 3 1/2" DP.