To re-iterate what we discussed this morning, Guerin have once again assured me that installation speed will increase after Songkran. Due to similar promises being made and broken previously we have agreed that if Guerin have not reduced the number of days they are behind schedule by Friday 25th April, then all of the workers on site will begin working overtime on weekday evenings and Saturdays, including Guerin’s engineers.
In order to ensure that Guerin are able to work at a fast rate, I need to receive more information from the Guerin team as to what they have achieved and what they are planning to do. We have therefore agreed that every Monday and Thursday, someone from Guerin will send me a brief email listing what has been installed since the previous email and what will be installed in the coming days.
I also need to receive by tomorrow a list of the dates on which Guerin plan to start work in the different areas. These dates are required so that I can push our civil contractors to have the spaces ready. In the absence of any information from Guerin I have thus far been allowing them to proceed at their own rate.