With regarding the fuel piping and skid structure steel is still HOLD and we had been ordered & received the raw material since November 2013 ( ~9 month). Please be informed you that some materials were rusted. Could you please advise us when we can start fabrication the fuel piping and skid structure support steel? If you have not any answer or confirmation from JKC within 15 Aug.14, we will transfer the raw material to other VPE project due to avoid material damage from heavy rust and may not be use in the future.