Contacting all permitting agencies and local administrations before construction commences, to
obtain a construction permission or to give them adequate notice
Contacting affected communities on site before construction commences, to ensure that they
are given adequate notice.
Survey and collect the communities’ data, Public utilities, Obstructions houses, Shops and
enterprises on site before construction commences.
Contacting and negotiating or compensating the owners to remove or relocation the public
utilities, obstructions houses, shops and enterprises.
Being available to the public private sectors and government agencies to answer queries and
ensure concerns and complaints are channeled to the correct person.
Contacting and turn back all area after construction to public and private and government
agencies.
Prepare CR Weekly report and submit to Owner.