4. What methodology was developed in the U.K., defines 45 separate subprocesses, and organizes
these into eight process groups?
a. Six Sigma
b. RUP
c. PMBOK® Guide
d. PRINCE2
5. Which of the following outputs is often completed before initiating a project?
a. stakeholder register
b. business case
c. project charter
d. kick-off meeting