4.6 Maintenance Services of the Contractor's Facility
(a) The Contractor, at its sole cost, including any transport, import, or export costs, shall conduct maintenance work in accordance with Good Industry Practice for the Contractor’s Facility to keep them in good condition at all time.
(b) The Contractor shall not remove any of the Contractor’s Facility from the Site during the Term without prior written consent of the Employer if such removal affects (or would be reasonably likely to affect) the performance of the Operation and Maintenance Services by the Contractor; provided that such consent will not be unreasonably withheld or delayed.