For your information and reference, the 2nd well location is PSC-G3 we have tentative plan to complete for land acquisition around this week. To be confirm for mob date again.
In order to get ready for site preparation please you submit us for the engineering package to review i.e. construction drawings including your organization chart for this project.
Your response in this require very highly appreciated.