Dear team,
Excellent documents from K. Bernie.
However, please note that scope of work is only hydro testing and gravity drain after tested. Including De-spading or reinstatement.
CLEANING BY WATER FLUSHING OR AIR BLOW IS EXCLUDED.
Basically, pipe cleaning will be done and continued after hydro testing complete.
Therefore, scope of work shall clarify with customer.