STAGE : 1
- INSTALL KING POST.
- INSTALL SLEEPER BEAM.
- INSTALL MAIN BEAM.
- INSTALL STEEL DECK SLAB.
- INSTALL HARD RAIL.
- INSTALLATION OF TEMPORARY CASING BY VIBRO HAMMER.
- EXCAVATION OF PILE TO FOUNDING LEVEL.
- INSTALLATION OF STEEL CAGES.
- CONCRETING OF PILE VIA TREMIE PIPE.
- EXTRACTION OF TEMPORARY CASING.
- INSTALL SHEET PILE & WALE STRUT.
- REMOVED PLATFORM OF GIRD LINE 1 TO 2
- EXCAVATE.