SUB-Contractor have to check the scope of work in the page 2 for more detail which item can supply or
cannot and SUB-contractor shall be identify in the quotation.
- General requirement
1) The owner factory is a hygiene product so all rule for safety requires is same as the refinery plant (i.e.
PTT).
2) Equipment as per above will install in the series start from EX-3201… to Z-3702 for final process.
3) Some equipment not requires fixing such as the EX-3201 or CA-3301 (They will install on the carbon
steel rail, rail install by civil).
4) Another item will fixed by anchor bolt installation.
5) Tolerance for all kind of equipment must within below:
± 0.03 mm/m in horizontal plane.
± 0.05 mm/m in parallel plane.
6) Require all inspection such as alignment, leveling, soft foot deviation or bolting location check,
SUB-Contract shall be perform document and procedure to submit OWNER and TNP also.
7) All equipment OWNER will supplied.
- Detail of Equipment.
1) TNP will provide equipment outline and detail for information to make quotation
2) TNP will sending 2 sets of drawing after SUB-Contractor receive this document, the document 2 set are
consist of type as below:
Set (1)
- Plant room layout 1 sheet.
- Plant room section layout 1 sheet.
- Plant room machine foundation layout 1 sheet.
Set (2)
- OS-3501 2 sheet.
- W-3701 4 sheet
- CA-3301 1 sheet
- ST-3401 2 sheet.
- Z-3701 3 sheet
- Unknown Equipment 4 sheet.
【SCHEDULE】
1) March 2016 – May 2016.
【WORK PLACE】