I request you all to start control O.T , as attached I see K.Wiwat (our RM-operator) has worked over than 19:00 pm in several days, and knowing that it caused from DRUM delay due to quality issues
and BPA from Bayer came late.
Pls put reason in PO requisition form (remark field) when submit to me for approval, and from now on each case of delay delivery which caused from vendor/ late clearance/ transportation, etc.
I request written evidence (e-mail) from vendor or persons in charge. Basically, I request all to allow our team for working O.T. not later than 19:00 pm.