CTH schedules to have shut down for maintenance during March 2-4,2015 (Monday to Wednesday of week 10th ).
The main purpose of this shutdown is an Acidulation buffer tank replacement. M&R will take this opportunity to do maintenance for other machines and systems as well.
A hand over from maintenance to production is aimed at 5:00 pm on Wednesday 4 of March. Except an Acidulation tank replacement which will continue until complete within next 3 days.
Particular on Tuesday 3th during 07:00 -24:00 . Whole Factory and office will have no electricity supply. A Temporary electricity will be supplied from generator at
1. Admin building
2. Control building
3. CMT building
The meeting room A1 at Admin building , B1 at control building and CMT will be available for people who are working at the building where no have electricity supply.
In order to optimize maintenance time during the outage. The freeze for request maintenance work order is on February 6th ,2015
M&R will organize on regular basis outage meetings
1. Please ensure that you create the work request in Ivara before the freezing date.
2. Please make sure that you /representatives of departments are present at these meetings.
3. Please provide timely detailed input to planner about plans and activities. In order to prevent issue due to conflicts in availability of people and equipment i.e. confined space permit
More information and updates will be informed frequently