The precedence relations between the tasks of work package 1 are of the finish-to-start type. These precedence relations represent a situation in which a task cannot start till all its predecessors are finished. For example tasks A and B can start as soon as the project starts since both have no predecessors, but task C can start only after its predecessor B is finished.