We are not clear ESP inspection and retrofitting work with damaged material list done by you but now here have not matching with your given schedule and manpower with required resources for this job
Also this job schedule(bar chart)who make nobody clear us. As per bar chart from 08.12.15 to 22.12.15 total 15 days. If this type of job in india done by our regular team/contactor take minimum 20 to 25 days.