Thanks for your summary.
As talked with K.Mania, we actually can’t accept this schedule. Now the rate is 120 cases per day (200 cases/day as planned) so it will take about 54 days for total gyoza order. With this rate, we will finish around end of Sep and we can nearly ETD the fourth container as original plan on 4 Oct.
I know that K.Mania did ask for some OT for the staff but can you give OT on some more days? and I also believe that we can get more productivity as the day pass so your staff will get used to with it and the rate will be higher than 120 cases/day.
Please can you try again to catch up the original plan for full gyoza on the fourth container.