“Clause 10:
The Sub-Contractor shall prepare both overall and fully detailed programmes for the approval of the Main Contractor. Once approved, the Sub-Contractor shall strictly comply therewith. To avoid any delay to progress, the Sub-Contractor shall fully co-ordinate all its activities with the Main Contractor AND with all other sub-contractors on site whose work or progress may be affected by the Sub-Contract Works. The Sub-Contractor shall also take all necessary steps to avoid possible causes and effects of delay”