Master schedule shall be attached to tender document and final version shall be attached to LOI or LOA. Progress shall be monitored in accordance with master schedule.
1. Master Schedule
Master schedule shall be attached to LOI and highly contractual. Progress shall be evaluated time by time for each activities.
2. Milestones
Milestones shall be shown in the master schedule such as commencement of installation works, major equipment delivery, utility receiving, start of T&C, training period, handing over date of each works. Mock up installation is one of milestone.
3. Testing and Commissioning Schedule
Testing and Commissioning Schedule shall be made. Power supply, Air side commissioning, Water side commissioning and Utility supply commissioning are major item.