Thank you for sending me kha. Please see my comments as follow: Normally,
• Civil contractor need to buy insurance to cover all loss/accident/damages which can be happened at our site but I didn’t see such requirement on their scope. It means that we don’t need or else
Reply : Thanks for remind. Normally, it will be the regular responsible of contractor and talk during negotiation. By the way, I will add it to the general scope.
• Civil contract will request for limit their liability/penalty. Do you think they will accept the non-identify maximum penalty/liability? If we are serious, we need to put the penalty higher than 0.1%. I think we are serious on the timeline, right? Why not we put the higher penalty for delay? Just curious
Reply : We do serious on project time line by the way, if we raise the high penalty cost, they may increase the price or not ?
• I think you put the wrong work completion date. It shall be 30 June 2016 not 2015
Reply : Thank you for this , I already changed it after sending.
• Please specify the item no. 2 “get bid back” to be “submit the closed envelop bid”
Reply : Ok, will specify submit with hard copy with the signature and CD of excel file 1 set.
• The utilities cost will be responsible by civil contractor, right?
Reply : Yes. Already identified.
• I didn’t see the project scope. I assume that it will be on the bidding documents, right? Ex. building size, road size, how many constructed buildings etc.
Reply : Yes, Since the less of drawings and blank BOQ are too big file. They will be attached to the CD for contractors.
• It’s turnkey project or just only civil part, kindly confirm
Reply : Civil only.
• Do we specify any “brand” or “specification” on the BOQ? Ex. steel size, concrete specification, any piling etc.
Reply : We have identified in detailed specification in drawing.
I’m sorry since I didn’t see the BOQ, can you share me the template?
Reply : Since they are big file, will update you on Monday.