Artinian project timeline has reached a critical stage, and I am very sure we will not be able to hand-over on June 20, 2014.
I would need you to do the following and we will have the discussion on June 16 at 9am in office (please do not be late as you have site meeting at Artinian at 10.30am and we also have Singapore Airlines to discuss).
1. New Project Delivery Schedule – please be realistic on a NEW HANDOVER DATE (I would need to inform Arto / Saro on this delay) ;
2. Each and every supplier & contractor delivery & install date for their scope of work (both material supply and installation work) ;
3. Who are the supplier / contractor that we have not issue PO for material / service (I need a clear list of supplier and product) ;
4. What are the pending item & finishes that has not been confirmed by Saro ?
5. Which are elevation drawing, etc. that is not finish ;
6. I need to know the M&E contractor completion date for AC / Data / Lighting, etc.. (those that is not under JHT) ;
On top of the above, please ensure that the following is completed on schedule as discussed previously :-
1. Costing for Artinian Level 9 (to give me before 12 noon on June 17, 2014) ;
2. Please revert to K. Yuii on the clarification of the 2 nos. VO so that she can forward that to Saro to confirm back (by June 16, 2014) ;
Other Project Issue :
1. Post Publishing Delivery Schedule to send to Post (??)