FS Team,
I'm sorry , I did not do oversight responsibilities.
Very surprising for such an operation, I am sure that it is not standard operating, normal operation is not allowed outside of the melt splash out, fortunately , we were stop work.
We very much hope get a compliance with safety and quality processes, but has continued to wait for four months.
In order to avoid continued past due, I decided to set up a new process, it shall comply with the requirements of safety and quality. My work instructions below:
1. Stop using modified sandwich ladle method.( it is substandard quality and unsafe operation )
2. Stop using plunging ladle method. (it is qualified quality but unsafe operation )
3. Using standard sandwich ladle method (it will provide qualified quality and safe operation )