Among the charts and diagrams created for project management, which of the
following is the most appropriate chart or diagram that can be used to visually check
the overall status of progress as well as the planned start and finish dates?
a) Arrow diagram b) Gantt chart
c) Cause and effect diagram d) Pareto chart