Dear, Khun Sakda
I would like to update the work re-install selective rack TASC-4, previously TTC vendor plan start on Monday 7th Dec,2015, But I worry with the work too late
Then push them coming start on tomorrow 3rd Dec,2015 and they stop on Sat & Sun (5-6) for holiday and come to start again on Monday 7th, that I think possible
Maybe they can do complete rack D & E (beside forklift way) first for support you team put the pallets , please advise
Dear, Khun Sakda I would like to update the work re-install selective rack TASC-4, previously TTC vendor plan start on Monday 7th Dec,2015, But I worry with the work too late Then push them coming start on tomorrow 3rd Dec,2015 and they stop on Sat & Sun (5-6) for holiday and come to start again on Monday 7th, that I think possibleMaybe they can do complete rack D & E (beside forklift way) first for support you team put the pallets , please advise