The criteria for measuring schedule effectiveness are those applied
to job-shops, and several approaches to resource-constrained multiple project scheduling use the job-shop model. A scarce resource required for several projects or by several different
activities in one project acts like a bottleneck in a manufacturing system. The bottleneck
acquires a waiting line or queue. A short digression into queuing theory is in order.