Sorry for late reply, The reason why we cannot achieve AFL because the land scorecard report was generated by un-updated data in CIP.
That means in case of changing loading date by suppliers (factory) which it will not be the same as CIP Plan but we have to follow the changed date and
we can deliver on time as suppliers‘ plan so far.
So the problem is data in CIP not updated. It should be updated as Suppliers’ plan day by day and then we will confirm, then the report will reflect our real performance