Implement 100% sorting before parts go to packing line (Short term)
Improvement for production layouts (Long term) :
Packing (Ongoing)
Edge banding (Ongoing)
BRUSALI series (Will be done on WK1603)
DOMBAS series (Ongoing)
Improving dust collecting system for drilling machine (Ongoing process)
Changing working process before lamination:
Sanding PB by SPSP (Short term)
Agree with sub-supplier to revise sanding process of PB (Long term)
Install anti stick system in edge banding machine (Long term)
Improve mindset and competence of co-workers (Long term – On process to follow up with SPS team how to be realistic actions):
AAA calibration, Q training
Direct communication from production manager to co-workers in production line
Implement “Right person to right job” concept