Dear Kh.Berry,
Summary reports of the meeting on 13 Nov 14, between Mr.Berry and Mr.Ron with details as follows
1.Conclusion : Truck scale room to it use original size is 2.5 x2.5 M
2.Conclusion : Conclusion: the space for installation of water tank for use in fire fighting. Is the side near Boiler
3.Wall behind control room. improve to the beauty in the picture below.
4.The retaining wall behind the factory waiting quotation from “Prairie”
5.Preparation document of steam machinery extension must be completed before the date 20 Nov 14,
6.Schedule for test run
- 24 Dec 14 Test Run Machinery : Action by Prairie
- 29 Dec 14 Test Run PLC : Action by CR Team
- 30 Dec 14 Test Run All System : Action By Prairie,CR Team,Cornucopia
- 5 Jan 14 Test Run By Product : Action By Prairie,CR Team,Cornucopia