ABB shall be requested of time extenaion to be May 10, 2015 which is refer to the last shipment, with waiver of liquidated damange. ABB and TL has agreed to compensate of all pump equipment to storage at ABB area for :-
MTP is storage until Oct 31, 2015
BV is storage until Feb 28, 2016
Which is no charge and zero balance.
Resolutions: All parties acknowledged.