Dear All,
Reference to the bi-weekly management meeting today. As discussed. Kindly find attached PFD for your reference.
1. PFD Decline Refurbishment –West Compartment’s Belt Conveyor:
a. Interface drawing: general connection layout of the equipment discharge the raw salt to tunnel conveyor.
For basic design of tunnel conveyor H5601Z
b. Arrangement drawing: how the material from tunnel conveyor (H5901Z) will be transferred to new salt storage as shown in Ercosplan flow sheet
For detail design of belt conveyor H5902Z and H5903Z)
2. PFD Tailing Pile and Generation of Tailing Pile(from Ercosplan Marcel Linder) – Need to confirm type of split or flattening operation equipment. Kindly advise.
3. PFD Raw Ore Storage – Apologies presented wrong PFD. Kindly ignore it.
Best Regards,