If the project proposal is revised by the Dialogue Partner, and if the change(s) in the project proposal revisions fulfil any or all of the following criteria, theproposal has to go through the Post CPR Approval process: (1) an upward or downward revision of total project cost of more than 25% from the initial amount, (2) change in ASEAN Sectoral Committee or Sub-Committee, (3) revision on scope and intended beneficiary(s), (4) revision on the objective(s) and intended outputs, and (5) a change of date or location considered as a major change.