Reference is made to PCPL’s letter ref. No. PCPL/C3/MRTA/L-1179-2015 dated October 14, 2015 considering on PAR JV’s notification for extension of time due to the Political Unrest. The committee (คณะกรรมการว่าด้วยการพัสดุ กรมบัญชีกลาง) define such event as the force majeure and relaxing the Contractor to serve notice in writing to their government’s client within 60 days from the letter’s endorsement ref. No. กค(กวพ.) 0421.3/ว291 dated August 20, 2015) with the condition as stated in the said letter and PAR JV also had served their notice in writing on September 29, 2015 which is within 60 days of the specified time from of the notification, PCPL recommended that PAR JV is entitled for such extension of time.