We are urgently arranging an additional shut-down schedule next week for two days on Sat/Sun. We already got green signal on this
from EGAT without penalty and have to confirm to EGAT as soon as possible. For clarification, in this alternative but more preferred
plan, we are to conduct BSI on one unit this week and the other unit next week. Of course, water washing works are on NNE.
But this plan deprives Keta san of his valuable holidays. In order for this plan to works, we have to check IHI's availability next week
for BSI. Subject to your availability, we believe this plan will allow enough time to fully check the engines and the whole package for
the later battle with EPC contractor.