Following Up
Structural Work
(All structural work will be completed by end of February)
- Level 6 (will be completed by Feb. 07)
- Level 7 (will be completed by Feb. 15)
- Roof top (will be completed by Feb. 15)
- Main Stair and Fire escape (will be completed by Feb. 28)
For all structural work details will be completed by Mid of March such as cut the piece of steel on the floor and clean every floor.