As current job site status is going reachable to start real hot commissioning next week for Unit 21 & very soon for
Unit 22 with look forward only 6-7 months left to achieve COD. Based on 779 items current status of “Drawing List
for Payment” is likely not much reflect the actual job site status & COD timing where around 50% of all items still
even couldn’t reach up more than 40% progress, we therefore would request you to have recheck again all of your
remaining list on the following point refer to summary table