This project is a study in order to reduce the time to change models quickly. The production of the production Line in Department polo shirt of D1, sewing factory, for example, the study found that the time it takes to change the production model takes quite a long time. Make output less than the target value. Causes of waiting tasks. The method of work of the employee that are not appropriate. Causes an imbalance of the production line, and is therefore looking for ways to improve the present principle of Quick Change Over to reduce the time it takes to modify the model, with the plant. By analyzing and developing machines for quick adjustment (Single Minute Exchange of Die: SMED) applied in garment factory finished. This method is called "Apparel SMED" in order to reduce the time it takes to change the production model.
Study results showed that can reduce the time it takes to change the version in the original production is reduced from 80 minutes to 30 minutes 62.5% percent when compared to the standard time in producing Polo shirts is 14.51 minutes per a, so can have more clothing options, which can be three, with increased productivity.