Dear Thomas,
Good Morning.
Additional information for this project.
Production process
1. Material are mixing between PET virgin and PET regrind 50:50 (Approx. BD. = 0.39 kg/l) and some time they use 100% regrind.
2. Drying material
3. The dried material is conveyed through a pipe to 500 kg. big bag.
4. Our customer would like to use 3 phase vacuum hopper loader for conveying dried material from 500 kg. big bag ( suck the material from 500 kg. big bag ) to their extruder.
vertical = 4-5 M. horizontal = 5 M.