K.Wang & Team,
I think we are having a constructive discussion. The fact is one thing and the opinion is the other. It is very common to have different opinions and we shared and think openly. This way we will get to a positive forward. Like in any case, we need to or try to understand the case(s), so that we can solve the problem. Pls keep this in mind. It would be beneficial to both Elite and PTTEP to get to understand the route cause(s) of this.
So I suggest the RM to capture the event log and the actions taken, together with the Liang. And make the suggestions of what could have done ect. And make the pump operation /maintenance procedure with manufacture manual etc. From there, we in the office will review /input. At the same time, you arrange to do the MPI for the high pressure line ASAP. And provide us the update.
This well is considered normal for 3 strings and in our plan we have checked the hydraulics, torque and drag etc., to ensure that the well can be drilled safely with the rig /equipment we have with the information provide to us from the contractors. So you can be sure of our engineering work in the planning process that factors had been considered