in order to rvacuate power to the system, PEA requires a new 115 kv transmission line connecting directly from the SPP delivery substation to a planned PEA substation to be named Chiyaphom 2 substation (possibly at Ban Lub Pho on HW -225,about 50 km from farm location). The Project Owner will be responsible for all costs of construction for the transmission system as well as additional equipment required to connect at the Chiyaphom 2 substation. However, if Chiyaphom 2 substation is still under construction at the time of SCOD, the Project Owner may temporarity connect directly to Chiyaphom substation which belongs to EGAT and is approximately 10 km away from Chiyaphom 2 substation