I have suggested in proposal that the two smaller lines delivered 5 months ex works, then large new factory 5.5 months then old factory can be 6 months or later.
I think this should be acceptable for them.
For terms and conditions, payment terms ok, penalty terms and dates in this contract to be discussed and finalised at last negotiation but in general ok.
Warranty: For Chinese supplied machine only accept max 18 months, we can do 27 months but then discount is 13% not 15%.
In general we have had very little problem with the Chinese frames supplied and if 27 months becomes critical we can discuss.
Price: The price includes max 15% discount to customer (please try better) and 3+3 commission.
I believe we have a very good overall solution for Thai Yazaki, it will be very nice and good rewinding lines.
I have also enclosed and updated layout, currently the Feed design unit is only for left to right line direction and hope this ok.
My travel schedule is booking up, so I only got next week and the week after available, then I will be away for two weeks.
I will be out of the office from your 11 am, but give me a call before you send the proposals.