Could you answer this ICCR because they are is part from stripping process.
Process of CA Frame stripping part
-Part NG return from F5 many problem. Some part from weld issue should rework by weld process, Some part scratch issue only stripping.
-If have rework by weld process QC will sent parts to production for rework should stick hold label and hang rework tag
-after production rework finish will sent return to QC.
-QC check all part if is a good part should take out hold label and rework tag (Finish process rework)
- QC request to PC for work order for sent to Hanger man
- After have work order QC will sent part to packing
- Packing response sent and receive part with Hanger man
- production recheck in CF and bung bolt sent to out work
- Packing response sent and receive part with JRR (ED part)
- After ED part sent to F5