Good morning Allen and Martin,
After some internal co-ordination meetings within Siriseang. Below is their current project status and requisition for delay in delivery.
In view of some unexpected construction site conditions, PTT has instructed Siriseang to slow down the construction operation.
We are sorry for our earlier prediction that PTT will get the permit in January 2016 had been delay. Updated information is PTT expect that they might get permit within midst of April 2016.
As you know from our previous report; Siriseang need permit to access to this construction site. And PTT need to get this permit from Thai government.
Based on current situation, our option is to seek the mill and CNooD co-operation to perform both External and Internal coating work in April 2016.
• Latest Shipment date : End of April 2016.
• Estimated Arrival in Bangkok : Midst of May 2016.
Hence, please help to convince the mill to re-scheduling of 3 LPE production date due to unexpected delay in the project site. We hope they can understand and support us.
Meanwhile, we look forward to your favourable reply.