As our site walk, please note we allow Ritta to hoard up the lift tower for sand wash work, wet work, plastering work etc. However Ritta have to provide the extra access beside the life tower for all party to access, loading and unloading. There are some issues highlighted on today;
- Leak found from roof top (luggage lift)
- As per installation standard/requirement, Ritta have to provide sufficient slope to drain out the water to drain outlet. This is to prevent moisture and damage to electrical device
Dear Khun Alex,
ZIEC shall complete the passenger lift decoration also prior to handover back to lift contractor.
Dear Khun Pornchai,
As our site walk, please note we allow Ritta to hoard up the lift tower for sand wash work, wet work, plastering work etc. However Ritta have to provide the extra access beside the life tower for all party to access, loading and unloading. There are some issues highlighted on today;- Leak found from roof top (luggage lift) - As per installation standard/requirement, Ritta have to provide sufficient slope to drain out the water to drain outlet. This is to prevent moisture and damage to electrical device Dear Khun Alex,ZIEC shall complete the passenger lift decoration also prior to handover back to lift contractor.Dear Khun Pornchai,
การแปล กรุณารอสักครู่..