Regarding to Subcon test volume, none of Subcon test is scheduled in WW39. Some of them has more test/hardware than loading so they should be able to complete test by Friday and ship back to BKK for mark/pack on Sat/Sun for Tue shipment. The only exception are VBM63 and TS56 KYEC that we are loading them in WW38 up to available hardware. Still we should be able to consider 75% of test volume to complete by Thu/Fri. In conclusion, I still think you accounted less Subcon volume than it should be in test analysis.
If FAB/FAC024 hardware does not come in time, it means we will cut 2.6 testers from analysis then at the end we should have 1.2 V5500 excess. My question is “can we commit more other packages that we still have hardware available such as LAE64, SPI, etc.?”